 | Level: Introductory Dean Leffingwell, Consultant, Consultant
03 Dec 2003 Software developers can improve project outcomes and deliver high-quality software on time, on budget, by working to reduce requirements errors. This white paper presents compelling reasons to invest in a more communicative and managed requirements assessment process.
Abstract
There is strong evidence to suggest that reducing requirements errors may be
the single most effective action application developers can take to improve
project outcomes and assist us in our goal
of delivering quality software,
on time and on budget
. This article highlights some of the empirical
evidence and demonstrates that an investment in more effective requirements
management can produce substantial rewards.
The Software Crisis Continues Unabated
In a June 1996 article in Fortune magazine cleverly titled " The Trouble with
Software Is ... It Sucks"
1
, industry
pundit Stewart Alsop lambasted our industry with his comments on the poor state
of software quality and reliability. While many in the industry take offense
at yet another broadside, a recent study by the Standish Group
2
, a well respected market research firm,
provided an even more sobering perspective. Specifically, according to the Standish
Group survey (over 352 companies reporting on over 8,000 software projects):
- 31% of all software projects are canceled before completed ($81 billion
waste)
- 53% of projects will cost 189% of estimates
- 9% on time and on budget (large companies)
- 16% on time and on budget (small companies)
In a further step to help understand the problem, the Standish Group survey
also asked its respondents to identify the causes of these failures. According
to the respondents, the top three reasons why projects were "impaired" are identified
in Table 1 below.
| Project Impairment Factors | % of Responses | | 1) Lack of User Input | 12.8% | | 2) Incomplete Requirements and Specifications | 12.3% | | 3) Changing Requirements and Specifications | 11.8% |
Table 1:
Standish Group Project Impairment Factors
It seems that our inability to work more effectively with users to better understand
their requirements, coupled with weak engineering discipline in managing requirements,
is the leading cause of software failures.
The High Cost of Requirements Errors
Studies performed at GTE, TRW, and IBM measured and assigned costs to errors
occurring at various phases of the project life-cycle
3
. These statistics were confirmed in later
studies
4
. Although these studies were run independently,
they all reached roughly the same conclusion: If a unit cost of one is
assigned to the effort required to detect and repair an error during the coding
stage, then the cost to detect and repair an error during the requirements stage
is between five to ten times less. Furthermore, the cost to detect
and repair an error during the maintenance stage is twenty times more.
Figure 1 below illustrates a summary of the results.
The reasons for this large difference is that many of these errors are not
detected until well after they have been made. This delay in error discovery
means that the cost to repair includes the cost to correct the offending error
and to correct subsequent investments in the error. These investments include
redesign of code, documentation rewrite, and the cost to rework or replace software
in the field.
Requirements errors are the most common errors
These studies illustrate that errors made in the requirements phase are extremely
expensive to repair. If such errors occurred infrequently, then the contribution
to overall cost would not be significant. However, requirements errors are indeed
the largest class of errors typically found in a complex software project. In
a study of a US Air Force project by Sheldon
5
, errors were classified by source. It was
found that requirements errors comprised 41% of the errors discovered, while
logic design errors made up only 28% of the total error count. Other studies
back this result. For example, Tavolato and Vincena, quoting Tom DeMarco, report
that 56% of all bugs can be traced to errors made during the requirements stage
6
.
Requirements Errors and Rework Costs
In a study performed at Raytheon, Dion reported that approximately 40% of the
total project budget was spent in rework costs
7
. Boehm reports that the cost of rework
can approach 50% for the largest software projects. Because of their large number,
and the multiplying effect, finding and fixing requirements errors consumes
between 70% - 85% of total project rework costs.
Reducing Requirements Errors
There is no silver bullet with which to make your requirements errors go away.
However, organizations have demonstrated that the following techniques are effective
in reducing these types of errors:
- More effective requirements elicitation
- Walkthroughs and reviews of requirements with customers and end users
- Better organization and documentation of requirements
- Accessible requirements repository, fostering improved team communication
- Improved reporting processes
- Better requirements-based testing and requirements traceability
In order to become proficient in these activities, an investment in both tools
and training for key project personnel will be required.
Estimating Typical Project and Rework Costs
Consider an application which contains 50,000 lines of code and is produced
by a staff of six developers supported by one program manager, two software
testers and one quality assurance person. To determine the product time line,
let's assume coding is the critical path (probably a defensible assumption in
most organizations!). Based upon a productivity rate of 350 lines of debugged
source code per month
8
, then the project timeline is 24 months.
(i.e. 50,000 LOC
face=Symbol>/350 LOC/month face=Symbol> 6 developers).
If the loaded cost per developer/tester/QA personnel per month is $10,000, then
that creates a total project budget of approximately $2.4 Million. Of this cost,
even if only 30% of the project is invested in rework (an optimistic assumption?),
then the total rework budget is $720,000. If 70% of the rework is due to requirements
errors, then the total rework costs related to requirements errors are over
half a million dollars!
| Typical Project | Your Project | | Number of lines of code | 50,000 | | | Number of developers | 6 | | | Person months of coding | 142.9 | | | Time to market | 24 calendar months | | | Loaded cost/team member/mo | $10,000 | | | Total project labor cost | $2,400,000 | | | Total rework costs (30%) | $720,000 | | | Total requirements errors rework cost (>>70%) | $504,000 | |
Table 2:
Project Cost Estimates for a Software Project
Your Investment
What's to be done to rework this valueless project activity? Simple,
REDUCE REQUIREMENTS ERRORS. The techniques demonstrated above could be expected
to have a dramatic effect on reducing requirements errors. However, as with
any meaningful process, an investment in both tools and training is required
for success. Let's assume that an organization purchases Requisite's RequisitePro
toolkit and training in both requirements management principles and tool usage
for the project staff. This would require an investment of approximately $19,900
[ten people *($995 tool+$995 training)]. How would this investment pay off?
The Bottom Line
No one can predict exactly how effective your organization will be in reducing
requirements errors. However, it seems reasonable to assume that a 20% or more
reduction in requirements errors can be accomplished at various levels of organizational
maturity. Because of the multiplying effect, any such reduction can have
a dramatic overall effect to your project's bottom line as Table 3 below shows.
| Case 1 | Case 2 | Case 3 | Your Project | | Requirements error reduction percentage | 10% | 20% | 40% | | | Cost savings on typical project | $50,400 | $100,800 | $201,600 | | | Months shaved off time-to-market | 1.0 | 1.7 | 2.5 | | | Payback time for investment in months | 9.5 | 4.7 | 2.4 | | | % Return on investment over life of First project
| 153% | 407% | 913% | |
Table 3: Return on Investment of More Effective Requirements Management
Summary
Table 3 above shows that the investment in requirements management tools and
training can provide a truly extraordinary payback even on the first project.
Thereafter, the team's ability to reduce requirements errors will continue to
pay a substantial dividend on future projects.
But these hard costs exclude the intangible costs associated with a requirements
error. Intangible costs include lack of features that could have been delivered
had the project's resources not been devoted to rework, loss of confidence on
the part of customers, and accompanying lost and unrecoverable market share,
revenue and profit.
Taken together, these costs clearly demonstrate that a company cannot afford
to ignore the benefits of better requirements management!
Bibliography
|
1.
| Alsop. S, "The Trouble with Software Is ... It Sucks", Fortune Magazine,
June 10, 1996 | |
2.
| The Standish Group, Chaos Report, 1994 | |
3.
| Davis, A., "Software Requirements - Objects, Functions and States", Prentice
Hall, 1993 | |
4.
| Boehm, B. and Papaccio, C. "Understanding and Controlling Software Costs",
IEEE Transactions of Software Engineering, Oct 1988 | |
5.
| Sheldon, F. et al, "Reliability Measurement from Theory to Practice",
IEEE Software, July 1992 | |
6.
| Tavolato, P., and K. Vincena. "A Prototyping Methodology and Its Tool."
In Approaches to Prototyping, R Budde et al., eds., Berlin: Springer-Verlag,
1984. | |
7.
| Dion, R. "Process Improvement and the Corporate Balance Sheet," IEEE Software,
(July 1993), pp. 28-35 | |
8.
| Grady, R. "Practical Software Metrics for Project Management and Process
Improvement", Prentice-Hall, Inc. 1992 |
About the author  | |  | Dean Leffingwell was Senior Vice President of Process and Project Management at Rational, and was responsible for methodology, the Rational Unified Process, customer education and training, and the company's products in the requirements, change request management, and project management disciplines. The lead author of Managing Software Requirements, A Unified Approach (Addison Wesley Longman, 1999), he holds an M.S. in engineering from the University of Colorado. |